Saltar navegación principal
Estás en: Home>Certificación>ProyectoMDL
Ficha Proyecto MDL

Datos del Proyecto:

Cucuana Hydroelectric Power Plant

The purpose of this project is to build a Hydroelectric Power Plant, with a total installed capacity of 55 MW in the Cucuana River, located in the Roncesvalles municipality, department of Tolima, Colombia. This project will collect the waters of the River in the point 2,195 meters above sea level, driving the water through an open channel to the machine house (three Pelton turbines). The electrical energy distribution line is rated at 115 KV and it is connected to the sub-station of Mirolindo, located in Ibagué, capital of the department of Tolima

País:
Colombia
Estado:
Validado
Documentación (inglés):
Inicio comentarios:
2008/08/02
Fin comentarios:
2008/08/31

Volver