Datos del Proyecto:

"Las Vacas" Hydroelectric project

The project activity consists of a hydroelectric plant with a installed capacity of 45 MW located at an reservoir on the Las Vacas river 18 kilometres northeast of Guatemala City. Construction of the first phase was finished on May 2002 with 20 MW, second and third phase of the Project to total 45 MW were available on May 2003. The hydroelectric plant is designed as a Peaking Plant in which water is stored in a reservoir in order to produce electricity during the peak demand hours.

País:
Guatemala
Estado:
Validado
Documentación (inglés):
Inicio comentarios:
2005/03/07
Fin comentarios:
2005/04/06
Comentarios :

Fecha comentario: 2005/04/05

País comentario: Estados Unidos de América

null

Fecha comentario: 2005/03/11

País comentario: Alemania

null